Back to smartelemfg Home
Contact us Merchants settle in
Back to smartelemfg Home
Home -Solution

Integrated EPC Solution for Steel Plant 33KV-11KV-0.4KV Substation

Source: Smartelecmfg 2025-06-18 16:16:01

1. Executive Summary
        This proposal provides a comprehensive EPC (Engineering, Procurement, Construction) solution for a 33KV-11KV-0.4KV substation, specifically designed for steel manufacturing plants. The solution covers electrical system design, equipment selection, protection & control, automation systems, and civil works, ensuring high reliability and continuous power supply for steel production. The system adheres to international standards (IEC, IEEE) and incorporates smart monitoring and energy management for remote operation and fault diagnostics, optimizing power safety and energy efficiency.

2. Design Scheme & Execution Process
2.1 Overall System Architecture
        The system adopts a three-stage voltage transformation:
        First Stage: 33KV → 11KV (Main Transformer)
        Second Stage: 11KV → 0.4KV (Distribution Transformer)
        Third Stage: 0.4KV power distribution

2.2 Capacity Calculation & Design
        Load Calculation (Based on IEC 61363)
        Using Demand Factor (DF) and Coincidence Factor (CF):
        Total Calculated Load = Σ (Equipment Rated Power × Demand Factor) × Coincidence Factor

Transformer Sizing (Based on IEC 60076, N-1 Redundancy Principle)
        Main Transformer Capacity:
        S = P / (cosφ × η) × 1.25 (Redundancy Factor)

Distribution Transformer:
        Configurations: 2×100% or 3×50% redundancy
        Grouped load calculation

Short-Circuit Current Calculation (IEC 60909 Standard)
Three-phase fault current analysis to verify breaking capacity of equipment

2.3 Execution Workflow
        Pre-Engineering Phase: Site survey, load analysis, grid data collection
        Design Phase: System design, protection coordination, layout planning
        Procurement Phase: International tendering, factory acceptance tests (FAT)
        Construction Phase: Civil works, equipment installation, cable laying
        Commissioning Phase: Individual tests, system integration, protection relay testing
        Operation Phase: Energization tests, performance verification, handover

3. Equipment List & System Components
3.1 Primary Equipment System
33KV Switchgear (IEC 62271 Standard)
GIS (Gas-Insulated Switchgear): SF6 insulation, including:
        Circuit Breaker (CB)
        Disconnector (DS)
        Earthing Switch (ES)
        Current Transformer (CT)
        Voltage Transformer (VT)
Function: 33KV incoming protection, metering, and distribution

Power Transformers (IEC 60076 Standard)
        33/11KV Main Transformer: Oil-immersed or dry-type, ONAN/ONAF cooling, with OLTC (On-Load Tap Changer)
        11/0.4KV Distribution Transformer: Dry-type, natural cooling
        Function: Voltage transformation & power transmission

11KV Switchgear (IEC 62271 Standard)
        AIS (Air-Insulated Switchgear) with vacuum circuit breakers (VCB)
        Includes: Feeder panels, bus coupler, PT panels
        Function: 11KV power distribution & protection

0.4KV LV Distribution System (IEC 61439 Standard)
        ACB (Air Circuit Breaker), MCCB (Molded Case CB), capacitor banks, distribution boards
        Function: Final distribution & power quality control

3.2 Secondary & Automation Systems
        Protection & Control System
        Microprocessor-based relays (overcurrent, differential, earth fault)
        IEC 61850 communication protocol
        Function: Fast fault isolation & system protection

SCADA System
        HMI (Human-Machine Interface)
        Data acquisition servers
        Historical database
        Function: Real-time monitoring & data management

Power Quality System
        Harmonic analyzer (IEC 61000-4-30)
        Reactive compensation (SVG/capacitor banks)
        Function: Ensures power quality compliance

Auxiliary Systems
        220VDC system
        UPS (Uninterruptible Power Supply)
        Environmental monitoring (temperature, humidity, SF6 detection)
        Function: Ensures control power reliability

4. Equipment Cost Breakdown
4.1 Major Equipment CostsThe equipment cost of a 35KV substation in a steel plant

4.2 Additional Costs
        Engineering Design: ~8-10% of equipment cost (~$400,000)
        Installation & Commissioning: ~15-20% of equipment cost (~$800,000)
        Civil Works: ~$500,000 (foundation, cable trenches)
        Project Management: ~5% of total cost (~$250,000)
        Total Estimated Cost: $6M–$7M (varies based on configuration)

5. Detailed Execution Steps
5.1 Engineering Phase (8–12 Weeks)
Basic Design:
        Grid parameter collection (short-circuit level, earthing method)
        Load survey & classification (IEC 60364)
        Single-line diagram finalization (single bus sectioned/double bus)

Detailed Design:
        Electrical calculations (short-circuit, protection coordination, cable sizing)
        Layout design (floor plan, elevation drawings)
        Protection logic & control schematics

Design Review:
        Internal 3-level verification
        Client approval meeting
        Utility approval (if required)

5.2 Procurement Phase (12–16 Weeks)
1).Tendering & Procurement:
       Technical specifications (IEC-based)
       International bidding (EU/Japanese brands preferred)
       Technical agreement negotiation

2).Factory Inspection:
       Witness testing (e.g., transformer FAT)
       Progress tracking
       Packaging & transport approval

5.3 Construction Phase (16–20 Weeks)
1)Civil Works:
       Substation foundation
       Cable trench construction
       Earthing grid (<0.5Ω resistance)

2)Equipment Installation:
       Transformer positioning (oil processing)
       Switchgear assembly
       Busbar connection (torque-controlled)

3)Cabling Works:
       HV cable laying & termination (IEC 60502)
       Control wiring
       Fiber optic splicing & testing

5.4 Commissioning Phase (6–8 Weeks)
1)Individual Tests:
       CB mechanical tests
       Relay calibration
       CT magnetization tests

2)System Integration:
       Protection coordination tests
       SCADA point-to-point verification
       Synchronization check

3)Energization Tests:
       24-hour no-load run
       Load testing (phase verification)
       Power quality measurement

5.5 Handover & Training (2–4 Weeks)
       1)Performance Validation:
       72-hour continuous operation
       100% protection accuracy verification
       Energy efficiency check

2)Documentation Delivery:
       As-built drawings
       O&M manuals
       Test reports

3)Training Program:
       System operation
       Preventive maintenance
       Troubleshooting drills

       Total Project Duration: 12–18 months (varies based on complexity).
       Critical Path: Equipment procurement & civil works.

       This EPC solution ensures seamless execution from design to commissioning, complying with international standards (IEC/IEEE) for steel plant substations.

Product recommendations More
PV DC Combiner Box
detail
PV AC Combiner Box
detail
440V/690V Low-Voltage Marine Switchboard
detail
15KV-10KV Outgoing Feeder Switchgear
detail
15KV-10KV Bus Tie Switchgear
detail
Inquiry Consultation
13655811378
13655811378
13655811378
13655811378
home product email
live chat
my